Print out a ditch petition sheet (Request for assistance)Updated November 2008
Recently
Completed Ditches
The Huenke #2 Ditch is located in St. Mary's Township Section 34. There are 85 acres in the watershed. The project included the installation of 1,980 feet of 10 inch plastic smooth interior tile and a railroad boring. The cost estimate for this project was $28,104.12.
Soon
To Be Constructed
The McKee Ditch is located in Logan Township Section 32 & 33 and crosses Moulton Fort Amanda Road. There are 210 acres in the watershed. The project will include the installation of 5,375 feet of plastic smooth interior tile. The cost estimate for this project is $82,267.13. The Burr Oak Ditch is located in Pusheta Township Section 18 and crosses Hardin Pike. There are 251 acres in the watershed. The project will include the installation of 2,964 feet of 18" plastic smooth interior tile. The cost estimate for this project is $64,636.99. The Easterly Ditch is located in Noble Township Section 10. There are 132 acres in the watershed. The project will include the installation of 3,675 feet of plastic smooth interior tile. The cost estimate for this project is $42,628.62. The Helmstetter Ditch is located in Duchouquest Township Section 19. There are 10 acres in the watershed. The project will include the installation of 1,127 feet of plastic smooth interior tile. The cost estimate for this project is $8,646.35 Ditches In Legal Meeting Stage
Ditches
in the Investigation and Design Stage
The Auglaize River Log Jam Removal Project is looking for funding. Doug Reinhart is applying for grants to help with the finance portion of the project and is hoping to have a meeting in the near future. The Kellermeyer #2 Ditch is located in St. Mary's Township Section 14. There are 320 acres in the watershed. This project will include the installation of 2,322 feet of 24 inch plastic smooth interior tile. The cost estimate for this project is $61,097.28. The Doenges Ditch is located in Noble Township Section 14. There are 195 acres in the watershed. This project will include the installation of 1,515 feet of plastic smooth interior tile. The cost estimate for this project is $28,313.68. The Fritz Ditch is located in Moulton Township Section 36. There are 344 acres in the watershed. The Kettler Ditch is located in St. Mary's Township Section 28,29,32 and 33. There are 770 acres in the watershed. The Kuenstle Ditch is located in Clay Township Section 4. There are 240 acres in the watershed. The Barrington Ditch is located in St. Mary's Township Section 31 and 32. There are 162 acres in the watershed.
|
|
|